JCT key dates calculator
Last reviewed September 2026
Enter the date of practical completion to get the key dates that follow under the JCT contracts: retention, the end of the Rectification Period, the final account and final payment, and limitation. Below that, work out the deadlines that run from common notices, including the 2024 change to extension of time decisions.
After practical completion
Periods and actual dates (optional)
The periods are the defaults in the unamended contract; change them to match yours. Enter actual dates once they’re known, and the dates that depend on them update.
Enter the date of practical completion to see the key dates.
Notice deadlines
How the dates are worked out
- Periods of days start the day after and leave out Christmas Day, Good Friday and bank holidays, as the JCT contracts provide. Periods of weeks, months and years run in calendar time.
- A period of months ends on the same date in the later month, or on the last day of a month that’s too short.
- Where a date depends on something that hasn’t happened yet, such as the final account documents arriving, the calculator assumes it happens on the last day allowed. Enter the actual dates to replace the assumptions.
- For payment dates during the job, use the payment notice calculator. For late completion, use the liquidated damages calculator.
Limitation
Time runs from the breach of contract, which for defective work can be earlier than practical completion, so treat the limitation date as a guide and take advice well before it. For defects in homes, claims under the Defective Premises Act 1972 have a 15-year limit, or 30 years for claims that arose before 28 June 2022, following the Building Safety Act 2022.
Before you rely on a date
This calculator is a guide to the standard periods, not legal advice. Check your contract, including any amendments and its rules on serving notices.
Sources
- JCT Design and Build and Standard Building Contracts 2016, part II: final accounts (JCT)
- JCT 2024: key changes in the new suite of contracts (BCLP)
- JCT 2024: the impact on time and cost claims (Burges Salmon)
- Limitation Act 1980, sections 5 and 8 (legislation.gov.uk)
- Building Safety Act 2022, section 135 (legislation.gov.uk)
More guides
- How much do building surveyors earn?
- What does a building surveyor do?
- How to become a building surveyor
- Chartered surveyor degree apprenticeships
- SAVA or an MSc?
- Building surveyor vs quantity surveyor
- Building control surveyors: salary and registration
- The APC for building surveyors
- Graduate building surveyor jobs
- Building surveyor interview questions
- Freelance building surveyors: day rates and going self-employed
- Building surveying in Australia
- The best books for building surveyors
- Survey equipment: a building surveyor’s kit list
- How does my salary compare?
- Party wall notice calculator
- Condensation and mould risk calculator
- Payment notice calculator
- Liquidated damages calculator